Some of the distribution system improvements being considered include the following;
1
Replace approximately 1000 LF infrastructure on 6” existing main with 8” DIP on Blue Ridge. Estimated cost of $400,000.
[Blue Ridge from 3rd Street to 1000 feet east]2
Replace approximately 200 LF infrastructure on 2” existing main with 6” DIP and add hydrants for improved fire protection. Estimated cost of $60,000.
[148th Circle and White]3
Replace approximately 700 LF infrastructure on 2” existing main with 6” DIP and add hydrants for improved fire protection along 138th Street. Estimated cost of $210,000
[138th Street east of Norby]4
Replace approximately 1,100 LF infrastructure on 4” existing main with 6” DIP and add hydrant for improved fire protection along Spruce. Estimated cost of $330,000.
[136th Street to 138th Street]5
Replace approximately 750 LF infrastructure on 4” existing main with 6” DIP and add hydrants for improved fire protection along Cypress. Estimated cost of $225,000.
[137th Street to 138th Street]6
Replace approximately 2200 LF infrastructure on 6” existing main with 6” DIP along Smalley Avenue and Southview Drive from 119th Terrace to end Cul-De-Sac. Estimated cost of $550,000.
7
Replace approximately 1300 LF infrastructure on 4” existing main with 6” DIP and add hydrants for improved fire protection along Belmont. Estimated cost of $390,000.
[137th Street to 139th Street]8
Replace approximately 660 LF infrastructure on 4” existing main with 6” DIP and add hydrants for improved fire protection along 137th Street. Estimated cost of $198,000.
[Belmont west to 6009 137th Street, 6009 137th Street to valve plat 34/S1]9
Install approximately 880 LF of new 10” DIP to connect to the existing 10” main at Newton Avenue South to the 10” main connection at the SE corner of 12023 Bennington Avenue. Estimated cost of $264,000.
10
Replace approximately 5000 LF infrastructure on 10” existing main with 12” DIP along Highgrove. Estimated cost of $2,000,000.
[East Outer Road to Byars Road]11
Replace approximately 1400 LF infrastructure on 4” existing main with 6” DIP and add hydrants for improved fire protection along 15th Street. Estimated cost of $420,000.
[135th Street to 133rd Street]12
Replace approximately 1400 LF infrastructure on 4” existing main with 6” DIP and add hydrants for improved fire protection along 13th Street. Estimated cost of $420,000.
[133rd Street to Highgrove]13
Replace approximately 1400 LF infrastructure on 4” existing main with 6” DIP and add hydrants for improved fire protection along Spring Street. Estimated cost of $420,000.
[135th Street to 133rd Street]14
Replace approximately 300 LF infrastructure on 6” existing main with 6” DIP and replace the hydrant. Estimated cost of $90,000.
[140th Street West Dunbar Ct.]15
Replace approximately 225 LF infrastructure on 6” existing main with 6” DIP and replace the hydrant. Estimated cost of $67,500.
[140th Street East Dunbar Ct.]16
Replace approximately 225 LF infrastructure on 6” existing main with 6” DIP and replace the hydrant. Estimated cost of $67,500.
[140th Street Dunoon Street]17
Replace approximately 225 LF infrastructure on 6” existing main with 6” DIP and replace the hydrant. Estimated cost of $67,500.
[140th Street Dornoch Street]18
Replace approximately 100 LF infrastructure on 6” existing main with 6” DIP 140th Street west street crossing. Estimated cost of $30,000.
[140th Street Dundee Circle]19
Replace approximately 100 LF infrastructure on 6” existing main with 6” DIP 140th Street west street crossing. Estimated cost of $30,000.
[140th Street Dundee Circle]20
Replace approximately 1600 LF infrastructure on 4” existing main with 6” DIP and add hydrants for improved fire protection along 149th Street. Estimated cost of $480,000.
[White Avenue to East Frontage Road]21
Transfer services and water connections from existing 6 inch to existing 12 inch approximately 4000 LF infrastructure along Grandview Road. Estimated cost of $250,000.
[Blue Ridge to Martha Truman]22
Replace approximately 1250 LF infrastructure on 6” existing main with 6” DIP and add hydrants for improved fire protection along High Drive. Estimated cost of $375,000.
[129th Street to Dead End]23
Replace approximately 1500 LF infrastructure on 6” existing main with 6” DIP and add hydrants for improved fire protection along Winchester. Estimated cost of $450,000.
[127th Street to 129th Street, East]24
Replace approximately 600 LF infrastructure on 6” existing main with 6” DIP and add hydrants for improved fire protection along Craig. Estimated cost of $180,000.
[127th Terrace to 127th Street, West]25
Replace approximately 1750 LF infrastructure on 6” existing main with 6” DIP and add hydrants for improved fire protection around The Grandview Middle School. Estimated cost of $525,000.
[127th Place]26
Replace approximately 1000 LF infrastructure on 6” existing main with 6” DIP and add hydrants for improved fire protection along 128th Street. Estimated cost of $300,000.
[Manchester to Sycamore]27
Replace approximately 1100 LF infrastructure on 6” existing main with 6” DIP and add hydrants for improved fire protection along 130th Street. Estimated cost of $330,000.
[Manchester to Sycamore]28
Replace approximately 1500 LF infrastructure on 6” existing main with 6” DIP and add hydrants for improved fire protection along Manchester. Estimated cost of $450,000.
[Park Hills to 134th Terrace]29
Replace approximately 1300 LF infrastructure on 6” existing main with 6” DIP and add hydrants for improved fire protection along Lowell. Estimated cost of $390,000.
[133rd Street to Highgrove]30
Replace approximately 1100 LF infrastructure on 6” existing main with 6” DIP and add hydrants for improved fire protection along Palmer. Estimated cost of $330,000.
[Manchester to 134th Terrace]31
Install waterline extension to serve The Greens at Grandview development, approximately 1200 LF infrastructure on new 8” DIP main to serve development including fire protection. Estimated cost of $450,000.
[147th Street and Byars]32
Install waterline extension to serve The Falcon Trails development, approximately 1500 LF infrastructure on new 6” DIP main to serve development including fire protection. Estimated cost of $300,000.
[3501 Blue Ridge]33
Install waterline extension to serve The River Oaks development, approximately 1650 LF infrastructure on new 6” DIP main to serve development including fire protection. Estimated cost of $350,000.
[St. Andrews to La Quinta]34
Install waterline extension to serve The Buck Stop Flats development, approximately 2000 LF infrastructure on new 8” DIP main to serve development including fire protection. Estimated cost of $400,000.
[150th and Bellair Avenue]